Re-roofing timetable Feb 2011

House Numbers Scaffold Erection Works Start Works End Scaffold Removed By
Phase One
145 to 148 N/A 07 February 2011 11 March 2011 18 March 2011
136 to 141 21 February 2011 28 February 2011 15 April 2011 22 April 2011
151 to 156 21 February 2011 28 February 2011 15 April 2011 22 April 2011
57 to 64 28 February 2011 07 March 2011 22 April 2011 29 April 2011
284 to 289 28 February 2100 10 March 2011 05 May 2011 10 May 2011
293 to 300 21 March 2011 28 March 2011 13 May 2011 20 May 2011
305 to 310 21 March 2011 28 November 2011 13 May 2011 20 May 2011
311 to 316 28 March 2011 04 April 2011 20 May 2011 27 May 2011
Phase Two
198 to 213 28 March 2011 06 April 2011 08 June 2011 21 June 2011
222 to 237 25 April 2011 05 May 2011 29 June 2011 12 July 2011
244 to 255 25 April 2011 05 May 2011 29 June 2011 12 July 2011
264 to 279 05 May 2011 17 May 2011 12 July 2011 22 July 2011
41 to 56 05 May 2011 17 May 2011 08 July 2011 21 July 2011
71 to 82 23 May 2011 02 June 2011 28 July 2011 09 August 2011
91 to 106 23 May 2011 02 June 2011 28 July 2011 09 August 2011
113 to 124 02 June 2011 14 June 2011 05 August 2011 17 August 2011
Phase Three
190 to 197 02 June 2011 09 June 2011 28 August 2011 03 August 2011
182 to 189 11 July 2011 18 July 2011 02 September 2011 09 September 2011
170 to 177 11 July 2011 18 July 2011 02 September 2011 09 September 2011
161 to 166 18 July 2011 25 July 2011 09 September 2011 16 September 2011
33 to 40 18 July 2011 25 July 2011 09 September 2011 16 September 2011
25 to 32 08 August 2011 15 August 2011 23 September 2011 30 September 2011
16 to 21 08 August 2011 15 August 2011 23 September 2011 30 September 2011
4 to 11 15 August 2011 22 August 2011 30 September 2011 07 October 2011
Site clearance & final handover 10 October 2011 21 October 2011

 